Hinkley Point (Drywall Systems)

client: Laing O’Rourke

Sector: Commercial

Hinley Point C workers accommodation campus providing en-suite accommodation and recreational facilities for 510 workers.

Our work at the Hinkley Point project spans 2 separate sites within the power-station scheme – Hinkley-C and Bridgwater-A.

Work on Bridgwater-A commenced in January 2018 whereas Hinkley-C completed in June.

This project threw up many logistical challenges with vehicular access for workers restricted at Hinkley-C which resulted in personnel being bussed in from park and ride sites across the region.

On both sites due to programme constraints we commenced partitions prior to the cladding being complete installing them ‘metal only’ to avoid water damage but gain programme time for the client.

The project in numbers

  • £1.25m

    project value

  • 20

    people

  • 46

    weeks